ANR Pipeline is taking bids through Friday on another binding open season to modify its Southeast Mainline System, this time specifically reversing flows on the line for up to 600,000 Dt/d of firm transportation capacity. In a open season notice issued March 7, ANR said it is seeking commitments for a more specific project: the reversal of 600,000 Dt/d from Zone ML3 to the ANR Southeast area Headstation Central Delivery Point, located in ML1 Tariff Rate Zone near Eunice, Louisiana. For the reversal, ANR expects to modify existing mainline facilities at compressor stations, including valves and yard piping, to enable bi-directional flow on ANR’s Southeast Mainline. The reversal project has an in-service date of March 1, 2015, earlier than the November 2015 service date for the pipeline’s prior binding open season, which was issued in late February. Article continues below… Request a free trial […]